Planned Projects

Larger extension and distribution-improvement works planned across the investment period, subject to funding and approval.

ProjectAreaScope
Murram–Kenyatta Road pipeline extensionJujaDN 315mm HDPE, 2.7km
Mugutha–Daykio pipeline extensionRuiruDN 250mm HDPE, approx. 800m
Distribution improvement, Jacaranda to Imani EstatesRuiruDN 250mm HDPE, 5.8km
Distribution improvement projectWeiteitheDN 315–250mm HDPE, 5.4km
Pipeline extensions across schemesRuiru, Juja & GithuraiDN 160–50mm HDPE, approx. 60km
Theta & Garong'ora distribution upgradeRuiruDN 560–250mm HDPE, 50km

Full detail on scope and per-year funding is available in our tariff and investment plan documents — see Downloads.